Design and Build Sewage Pump Station – Contract No. 2, Airport Area, Jeddah City, Saudi Arabia
Project Partners:
| Role |
Organization |
| Owner | National Water Company (NWC) |
| Consultant | Bayt Al Khibra for Engineering Consultants |
| Main Contractor | Thrustboring Construction Co. Ltd. |
| Subcontractor | EPF General Contracting Co. |
| Project Group | Tamimi Group |
This project involves the Design and Construction of a Sewage Pump Station located near the Airport area in Jeddah City, under the National Water Company’s (NWC) infrastructure development initiative.
Quality & Safety Compliance:
EPF prioritizes safety and quality as integral to its operations.
• All workers are equipped with mandatory PPE (helmets, vests, gloves, and safety boots).
• Formwork and rebar works are conducted under strict HSE supervision.
• Materials and workmanship are tested and inspected regularly as per consultant and client specifications.
The Sewage Pump Station (Contract No. 2) in Jeddah represents a vital infrastructure initiative aimed at improving wastewater management efficiency in the airport region.
EPF General Contracting is proud to contribute to this national development project in partnership with TCC, Bayt Al Khibra, and NWC, ensuring timely delivery with the highest standards of engineering, safety, and quality.
Current Work Progress:
EPF General Contracting has successfully mobilized its site team and resources, initiating foundation-level activities.
Project Update – November 2025
Phase 6
Wall Reinforcement & Formwork Phase
Vertical rebar installation and chamber wall formwork are ongoing. EPF teams are aligning reinforcement and preparing wall segments for the next concrete pour.
↓
Phase 5
Concrete Pouring Phase
Controlled concrete pumping for the footing bases completed under consultant supervision. Compaction and curing are performed as per QA/QC standards.
↓
Phase 4
Reinforcement & Structural Assembly
Heavy reinforcement cages positioned and tied in the deep foundation pit. Complete rebar grid inspection done before concrete pour approval.
↓
Phase 3
Waterproofing & Pre-Casting
Bituminous surface coating applied for waterproofing and base protection prior to reinforcement installation.
↓
Phase 2
Foundation Formwork & Rebar Installation
Timber formwork and rebar layout prepared for multiple footing zones. Final bracing and QA checks completed before casting.
↓
Phase 1
Site Preparation & Layout
Site clearing, leveling, and base excavation completed. Foundation layout and grid marking verified by the consultant.
📍 Project Location: Airport Area, Jeddah City, Kingdom of Saudi Arabia